On September 29, 2005, the Board of Trustees
voted to postpone the decision of building the Parking Structure until
a later date.
The Board of Trustees is currently re-evaluating the need for a parking
structure.The design development for the Parking
Structure is completed. The Board of Trustees is currently reviewing
options for the structural system (pre-cast vs. cast-in-place concrete).
Once the analysis is complete, the project will resume the construction
documents phase.Design development work is progressing.
The project is on schedule. On March 17, the Board of Trustees approved
the schematic design for this project. Design development will begin
immediately and is currently scheduled for completion in April 2005.
A schematic design presentation was given at the February Board of
Trustees Meeting. After approval of schematic design by the Board,
the design development phase will begin.
Schematic design is approximately 75 percent complete. Schematic design
presentation for Board approval is currently scheduled for March 2005.
The Parking Structure is currently in the schematic
design phase. In October 2004, the College of DuPage Board of Trustees
approved a contract award for design services to Walker Parking Consultants.